Dept. of Trans. PROGRESS Serial No. Contract No. 10-356-14-43 11-278004 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 99% 98% 11-IMP-78-41.1/63.0 Federal Project: NONE Progress payment No. 03 Payment period ending: 12-20-10 WEST COAST PAVING AND CHIP SEALING P O BOX 1231 YREKA CA 96097 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 1,098,093.88 217,750.48 2.a. Extra Work b. Adjustment Comp. -750.00 -750.00 3. Materials on Hand 4. Earned Subject to Retention 1,097,343.88 217,000.48 5. Mobilization 15,000.00 0.00 6. Total Work Completed 1,112,343.88 7. Deductions -149,620.69 -145,972.10 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 962,723.19 71,028.38 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 71,028.38