Dept. of Trans. PROGRESS Serial No. Contract No. 07-170-13-52 11-280104 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 78% 89% 11-SD-805-6.0/6.2 Federal Project: NONE Progress payment No. 03 Payment period ending: 06-20-07 HAZARD CONSTRUCTION COMPANY P O BOX 229000 SAN DIEGO CA 921929000 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 603,037.53 263,308.32 2.a. Extra Work 6,913.62 6,913.62 b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 609,951.15 270,221.94 5. Mobilization 77,000.00 3,850.00 6. Total Work Completed 686,951.15 7. Deductions -10,000.00 0.00 8. a.Contract Retentions -30,497.56 -13,511.10 b. Unsatisfactory Prog. -13,511.09 -13,511.09 c. Reduction after 95% Comp. 9. Total pay to Contractor 632,942.50 247,049.75 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 247,049.75