Dept. of Trans. PROGRESS Serial No. Contract No. 08-113-08-45 11-281004 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 52% 38% 11-SD-76-R8.0/37.9 Federal Project: NONE Progress payment No. 02 Payment period ending: 04-20-08 ZONDIROS CORPORATION 1833 DIAMOND STREET STE 201 SAN MARCOS CA 92078 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 153,920.80 149,342.80 2.a. Extra Work b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 153,920.80 149,342.80 5. Mobilization 142,500.00 142,500.00 6. Total Work Completed 296,420.80 7. Deductions -88,470.17 -88,470.17 8. a.Contract Retentions -8,374.70 -7,916.90 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 199,575.93 195,455.73 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 195,455.73