Dept. of Trans. PROGRESS Serial No. Contract No. 07-354-12-32 11-281104 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 98% 94% 11-IMP-111-23.9/40.5 Federal Project: NONE Progress payment No. 03 Payment period ending: 12-20-07 INTERNATIONAL SURFACING SYSTEMS P O BOX 4770 MODESTO CA 95352 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 574,132.52 2,504.00 2.a. Extra Work 2,367.08 2,367.08 b. Adjustment Comp. 13,454.35 13,454.35 3. Materials on Hand 4. Earned Subject to Retention 589,953.95 18,325.43 5. Mobilization 35,427.00 0.00 6. Total Work Completed 625,380.95 7. Deductions -23,969.14 -3,594.14 8. a.Contract Retentions -29,497.70 -916.27 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 571,914.11 13,815.02 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 13,815.02