Dept. of Trans. PROGRESS Serial No. Contract No. 07-233-15-35 11-281304 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 93% 96% 11-IMP-8-R29.7/R30.1 Federal Project: NONE Progress payment No. 03 Payment period ending: 08-20-07 DALEY CORPORATION 5370 EASTGATE MALL SAN DIEGO CA 92121 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 405,686.53 225,641.30 2.a. Extra Work 3,383.19 1,254.66 b. Adjustment Comp. 4,529.11 4,529.11 3. Materials on Hand 4. Earned Subject to Retention 413,598.83 231,425.07 5. Mobilization 10,000.00 500.00 6. Total Work Completed 423,598.83 7. Deductions -10,000.00 -10,000.00 8. a.Contract Retentions -20,679.94 -11,571.25 b. Unsatisfactory Prog. 0.00 8,938.29 c. Reduction after 95% Comp. 9. Total pay to Contractor 392,918.89 219,292.11 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 219,292.11