Dept. of Trans. PROGRESS Serial No. Contract No. 17-081-14-28 11-282304 PROGRESS PAYMENT VOUCHER %complete: %time: 88% 40% Location: Federal Project: 11-SD-5-31.7/31.7 STPI-005-1(630) Progress payment No. 017 Payment period ending: 03-20-17 HAZARD CONSTRUCTION COMPANY 6465 MARINDUSTRY DR SAN DIEGO CA 92121 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 670,997.65 1,828.00 2. a. Extra Work 972.54 0.00 b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 671,970.19 1,828.00 5. Mobilization 80,000.00 0.00 6. Total Work Completed 751,970.19 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 751,970.19 1,828.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 1,828.00