Dept. of Trans. PROGRESS Serial No. Contract No. 14-083-15-03 11-282404 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 13% 8% 11-SD-15-0.0/4.7 Federal Project: NHP-X073(103) Progress payment No. 02 Payment period ending: 03-20-14 WESTERN RIM CONSTRUCTORS INC 912 S ANDREASEN DR STE 108 ESCONDIDO CA 92029 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 228,219.89 91,726.86 2.a. Extra Work b. Adjustment Comp. 3. Materials on Hand 16,724.39 16,724.39 4. Earned Subject to Retention 244,944.28 108,451.25 5. Mobilization 133,414.74 0.00 6. Total Work Completed 361,634.63 7. Deductions -10,000.00 -10,000.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 368,359.02 98,451.25 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 98,451.25