Dept. of Trans. PROGRESS Serial No. Contract No. 14-295-07-58 11-282404 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 85% 44% 11-SD-15-0.0/4.7 Federal Project: NHP-X073(103) Progress payment No. 09 Payment period ending: 10-20-14 WESTERN RIM CONSTRUCTORS INC 912 S ANDREASEN DR STE 108 ESCONDIDO CA 92029 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 2,247,226.46 238,749.56 2.a. Extra Work 47,962.43 17,376.91 b. Adjustment Comp. 15,171.33 15,171.33 3. Materials on Hand 1,946.82 -19,245.89 4. Earned Subject to Retention 2,312,307.04 252,051.91 5. Mobilization 266,829.47 0.00 6. Total Work Completed 2,577,189.69 7. Deductions -13,000.00 -3,000.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 2,566,136.51 249,051.91 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 249,051.91