Dept. of Trans. PROGRESS Serial No. Contract No. 14-356-08-33 11-282404 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 93% 57% 11-SD-15-0.0/4.7 Federal Project: NHP-X073(103) Progress payment No. 11 Payment period ending: 12-20-14 WESTERN RIM CONSTRUCTORS INC 912 S ANDREASEN DR STE 108 ESCONDIDO CA 92029 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 2,478,253.74 9,052.36 2.a. Extra Work 104,622.55 56,660.12 b. Adjustment Comp. 4,371.33 -10,800.00 3. Materials on Hand 0.00 -529.86 4. Earned Subject to Retention 2,587,247.62 54,382.62 5. Mobilization 266,829.47 0.00 6. Total Work Completed 2,854,077.09 7. Deductions -13,000.00 -3,000.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 2,841,077.09 51,382.62 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 51,382.62