Dept. of Trans. PROGRESS Serial No. Contract No. 15-111-13-00 11-282504 PROGRESS PAYMENT VOUCHER %complete: %time: 9% 8% Location: Federal Project: 11-SD-15 NHP-X073(109) Progress payment No. 001 Payment period ending: 04-20-15 WESTERN RIM CONSTRUCTORS, INC. 912 S ANDREASEN DR SUITE 108 ESCONDIDO CA 92029 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 241,137.69 241,137.69 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 241,137.69 241,137.69 5. Mobilization 159,812.55 159,812.55 6. Total Work Completed 400,950.24 7. Deductions -1,000.00 -1,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 399,950.24 399,950.24 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 399,950.24