Dept. of Trans. PROGRESS Serial No. Contract No. 16-078-15-51 11-282504 PROGRESS PAYMENT VOUCHER %complete: %time: 92% 50% Location: Federal Project: 11-SD-15 NHP-X073(109) Progress payment No. 013 Payment period ending: 03-20-16 WESTERN RIM CONSTRUCTORS INC. 621 S ANDREASEN DR #B ESCONDIDO CA 92029 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 3,753,011.51 91,481.67 2. a. Extra Work 201,573.37 -4,338.35 b. Adustment Comp. 31,460.90 0.00 3. Materials on Hand 4. Earned Subject to Retention 3,986,045.78 87,143.32 5. Mobilization 319,625.09 0.00 6. Total Work Completed 4,305,670.87 7. Deductions -3,000.00 -1,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 4,302,670.87 86,143.32 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 86,143.32