Dept. of Trans. PROGRESS Serial No. Contract No. 17-171-11-37 11-282504 PROGRESS PAYMENT VOUCHER %complete: %time: 98% 80% Location: Federal Project: 11-SD-15 NHP-X073(109) Progress payment No. 027 Payment period ending: 06-20-17 WESTERN RIM CONSTRUCTORS INC. 621 S ANDREASEN DR #B ESCONDIDO CA 92029 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 3,887,149.53 4,446.14 2. a. Extra Work 408,413.96 13,275.21 b. Adustment Comp. 84,890.09 -3,138.34 3. Materials on Hand 4. Earned Subject to Retention 4,380,453.58 14,583.01 5. Mobilization 319,625.09 0.00 6. Total Work Completed 4,700,078.67 7. Deductions -32,000.00 -10,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 4,668,078.67 4,583.01 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 4,583.01