Dept. of Trans. PROGRESS Serial No. Contract No. 07-330-14-18 11-282804 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 52% 90% 11-SD-76-R1.5/R5.0 Federal Project: NONE Progress payment No. 03 Payment period ending: 11-20-07 3 D ENTERPRISES INCORPORATED 2180 GARNET STE 26 SAN DIEGO CA 92109 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 107,358.00 84,558.00 2.a. Extra Work b. Adjustment Comp. -22,000.00 -22,000.00 3. Materials on Hand 4. Earned Subject to Retention 85,358.00 62,558.00 5. Mobilization 14,250.00 3,000.00 6. Total Work Completed 99,608.00 7. Deductions 0.00 2,642.40 8. a.Contract Retentions -4,267.90 -1,987.90 b. Unsatisfactory Prog. -3,127.90 -3,127.90 c. Reduction after 95% Comp. 9. Total pay to Contractor 92,212.20 63,084.60 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 63,084.60