Dept. of Trans. PROGRESS Serial No. Contract No. 08-171-12-53 11-282804 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 98% 100% 11-SD-76-R1.5/R5.0 Federal Project: NONE Progress payment No. 10 Payment period ending: 06-20-08 3 D ENTERPRISES INCORPORATED 2180 GARNET STE 26 SAN DIEGO CA 92109 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 187,106.00 0.00 2.a. Extra Work 79,700.03 29,775.69 b. Adjustment Comp. -16,199.54 0.00 3. Materials on Hand 4. Earned Subject to Retention 250,606.49 29,775.69 5. Mobilization 15,000.00 0.00 6. Total Work Completed 265,606.49 7. Deductions 8. a.Contract Retentions -12,530.32 -1,488.78 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 253,076.17 28,286.91 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 28,286.91