Dept. of Trans. PROGRESS Serial No. Contract No. 09-142-13-23 11-283704 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 98% 100% 11-SD-52-4.9/6.2 Federal Project: NONE Progress payment No. 05 Payment period ending: 05-20-09 HAZARD CONSTRUCTION COMPANY P O BOX 229000 SAN DIEGO CA 921929000 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 1,308,939.25 14,501.20 2.a. Extra Work 73,450.05 20,678.05 b. Adjustment Comp. -49,740.80 -1,801.67 3. Materials on Hand 4. Earned Subject to Retention 1,332,648.50 33,377.58 5. Mobilization 145,000.00 0.00 6. Total Work Completed 1,477,648.50 7. Deductions -4,450.12 -1,450.12 8. a.Contract Retentions -66,632.43 -1,668.88 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 1,406,565.95 30,258.58 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 30,258.58