Dept. of Trans. SEMI-FINAL Serial No. Contract No. 09-280-10-25 11-283704 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 100% 100% 11-SD-52-4.9/6.2 Federal Project: NONE Progress payment No. 08 Payment period ending: 06-30-09 HAZARD CONSTRUCTION COMPANY P O BOX 229000 SAN DIEGO CA 921929000 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 1,309,689.25 0.00 2.a. Extra Work 186,583.19 22,668.84 b. Adjustment Comp. -46,065.80 3,675.00 3. Materials on Hand 4. Earned Subject to Retention 1,450,206.64 26,343.84 5. Mobilization 145,000.00 0.00 6. Total Work Completed 1,595,206.64 7. Deductions 0.00 1,000.00 8. a.Contract Retentions -67,789.62 0.00 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 67,789.62 0.00 9. Total pay to Contractor 1,595,206.64 27,343.84 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 27,343.84