Dept. of Trans. PROGRESS Serial No. Contract No. 08-234-14-49 11-284004 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 89% 98% 11-IMP-8-R83.6/R84.0 Federal Project: NONE Progress payment No. 02 Payment period ending: 08-20-08 BEADOR CONSTRUCTION COMPANY INC 26320 LESTER CIRCLE CORONA CA 92883 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 433,725.39 378,764.35 2.a. Extra Work b. Adjustment Comp. 3,338.98 0.00 3. Materials on Hand 4. Earned Subject to Retention 437,064.37 378,764.35 5. Mobilization 24,347.00 6,086.75 6. Total Work Completed 461,411.37 7. Deductions -16,260.80 -9,362.00 8. a.Contract Retentions -21,853.22 -16,023.22 b. Unsatisfactory Prog. -18,938.22 -18,938.22 c. Reduction after 95% Comp. 9. Total pay to Contractor 404,359.13 340,527.66 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 340,527.66