Dept. of Trans. PROGRESS Serial No. Contract No. 10-168-13-39 11-284304 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 99% 100% 11-SD-5-9.6/R26.2 Federal Project: OTS Progress payment No. 10 Payment period ending: 06-20-10 HAZARD CONSTRUCTION COMPANY P O BOX 229000 SAN DIEGO CA 921929000 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 3,246,704.45 -35,501.20 2.a. Extra Work 93,184.74 28,576.09 b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 3,339,889.19 -6,925.11 5. Mobilization 367,000.00 0.00 6. Total Work Completed 3,706,889.19 7. Deductions 0.00 7,000.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 3,706,889.19 74.89 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 74.89