Dept. of Trans. FINAL Serial No. Contract No. 09-135-08-30 11-284504 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 100% 100% 11-IMP-86-15.1/15.5 Federal Project: NONE Progress payment No. 06 Payment period ending: 08-08-08 HAZARD CONSTRUCTION COMPANY P O BOX 229000 SAN DIEGO CA 921929000 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 510,942.94 0.00 2.a. Extra Work 25,530.36 0.00 b. Adjustment Comp. -6,744.00 -7,200.58 3. Materials on Hand 4. Earned Subject to Retention 529,729.30 -7,200.58 5. Mobilization 53,000.00 0.00 6. Total Work Completed 582,729.30 7. Deductions 0.00 18,000.00 8. a.Contract Retentions -25,442.93 0.00 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 25,442.93 0.00 9. Total pay to Contractor 582,729.30 10,799.42 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 10,799.42