Dept. of Trans. AFTER ACCEPTANCE Serial No. Contract No. 08-161-08-03 11-284904 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 100% 100% 11-SD-94-R10.4/14.9 Federal Project: NONE Progress payment No. 09 Payment period ending: 05-30-08 VALLEY SLURRY SEAL COMPANY P O BOX 981330 WEST SACRAMENTO CA 95798 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 895,780.73 40,841.82 2.a. Extra Work b. Adjustment Comp. 27,799.84 -1,500.00 3. Materials on Hand 4. Earned Subject to Retention 923,580.57 39,341.82 5. Mobilization 55,250.00 0.00 6. Total Work Completed 978,830.57 7. Deductions -12,000.00 -12,000.00 8. a.Contract Retentions -44,211.94 0.00 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 44,211.94 44,211.94 9. Total pay to Contractor 966,830.57 71,553.76 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 71,553.76