Dept. of Trans. PROGRESS Serial No. Contract No. 09-355-15-58 11-286004 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 24% 40% 11-SD-5-5.4/5.4 Federal Project: ACHS-051(609) IMG-051(609) Progress payment No. 03 Payment period ending: 12-20-09 DBX INC 42066 AVENIDA ALVARADO STE C TEMECULA CA 92590 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 145,652.72 13,114.00 2.a. Extra Work b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 145,652.72 13,114.00 5. Mobilization 21,614.40 4,550.40 6. Total Work Completed 167,267.12 7. Deductions -2,000.00 -2,000.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 165,267.12 15,664.40 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 15,664.40