Dept. of Trans. PROGRESS Serial No. Contract No. 10-112-09-16 11-286004 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 68% 93% 11-SD-5-5.4/5.4 Federal Project: ACHS-051(609) IMG-051(609) Progress payment No. 07 Payment period ending: 04-20-10 DBX INC 42066 AVENIDA ALVARADO STE C TEMECULA CA 92590 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 452,593.54 104,370.11 2.a. Extra Work 5,455.50 2,456.75 b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 458,049.04 106,826.86 5. Mobilization 22,752.00 0.00 6. Total Work Completed 480,801.04 7. Deductions 0.00 2,000.00 8. a.Contract Retentions b. Unsatisfactory Prog. -20,438.15 -10,682.69 c. Reduction after 95% Comp. 9. Total pay to Contractor 460,362.89 98,144.17 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 98,144.17