Dept. of Trans. SEMI-FINAL Serial No. Contract No. 11-192-13-11 11-286604 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 100% 100% 11-SD-8-L1.2/ .0 Federal Project: ACIM-008-1(306) Progress payment No. 05 Payment period ending: 05-17-11 TRAFFIC DEVELOPMENT SERVICES INC 4215 TIERRA REJADA RD STE 184 MOORPARK CA 93021 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 459,752.64 0.00 2.a. Extra Work 75,934.91 44,308.92 b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 535,687.55 44,308.92 5. Mobilization 25,000.00 0.00 6. Total Work Completed 560,687.55 7. Deductions -15,000.00 0.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 545,687.55 44,308.92 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 44,308.92