Dept. of Trans. FINAL Serial No. Contract No. 09-048-09-47 11-287504 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 100% 100% 11-IMP-86-R33.3/43.1 Federal Project: NONE Progress payment No. 05 Payment period ending: 04-17-08 PAVE TECH INC 735 LAGUNA DR CARLSBAD CA 92008 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 580,628.51 0.00 2.a. Extra Work 8,847.28 0.00 b. Adjustment Comp. 143,903.45 0.00 3. Materials on Hand 4. Earned Subject to Retention 733,379.24 0.00 5. Mobilization 31,000.00 0.00 6. Total Work Completed 764,379.24 7. Deductions -1,000.00 10,000.00 8. a.Contract Retentions -28,757.16 0.00 b. Unsatisfactory Prog. c. Reduction after 95% Comp. 28,757.16 0.00 9. Total pay to Contractor 763,379.24 10,000.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 10,000.00