Dept. of Trans. FINAL Serial No. Contract No. 15-203-07-58 11-287704 PROGRESS PAYMENT VOUCHER %complete: %time: 100% 100% Location: Federal Project: 11-SD-5506 NONE Progress payment No. 016 Payment period ending: 01-06-15 KINSMAN CONSTRUCTION INC 6711 NANCY RIDGE DRIVE SAN DIEGO CA 92121 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 1,356,829.00 0.00 2. a. Extra Work 521,404.55 0.00 b. Adustment Comp. 103,742.00 0.00 3. Materials on Hand 4. Earned Subject to Retention 1,981,975.55 0.00 5. Mobilization 6. Total Work Completed 1,981,975.55 7. Deductions 0.00 13,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 1,981,975.55 13,000.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 13,000.00