Dept. of Trans. PROGRESS Serial No. Contract No. 09-355-15-58 11-288104 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 38% 75% 11-IMP-86-4.4/4.7 Federal Project: NONE Progress payment No. 02 Payment period ending: 12-20-09 T D S ENGINEERING 1014 S WESTLAKE BLVD STE 1413 WESTLAKE VILLAGE CA 91361 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 110,369.12 108,844.12 2.a. Extra Work b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 110,369.12 108,844.12 5. Mobilization 14,250.00 14,250.00 6. Total Work Completed 124,619.12 7. Deductions 8. a.Contract Retentions b. Unsatisfactory Prog. -10,884.41 -10,884.41 c. Reduction after 95% Comp. 9. Total pay to Contractor 113,734.71 112,209.71 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 112,209.71