Dept. of Trans. PROGRESS Serial No. Contract No. 10-203-07-57 11-288804 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 32% 30% 11-SD-905-R9.5/R15.0 Federal Project: SARR-A905(19) A-A905(19) Progress payment No. 14 Payment period ending: 07-20-10 FLATIRON WEST SUKUT CONSTRUCTION A JOINT VENTURE 1770 LA COSTA MEADOWS DRIVE SAN MARCOS CA 92078 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 13,179,724.08 980,639.25 2.a. Extra Work 603,285.62 38,004.85 b. Adjustment Comp. 41,858.23 33,709.78 3. Materials on Hand 616,851.20 154,848.81 4. Earned Subject to Retention 14,441,719.13 1,207,202.69 5. Mobilization 4,655,000.00 0.00 6. Total Work Completed 18,479,867.93 7. Deductions -35,305.18 -3,000.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 19,061,413.95 1,204,202.69 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 1,204,202.69