Dept. of Trans. PROGRESS Serial No. Contract No. 17-023-13-42 11-288814 PROGRESS PAYMENT VOUCHER %complete: %time: 96% 50% Location: Federal Project: 11-SD-905-R10.6 CBI-X073(111) Progress payment No. 017 Payment period ending: 01-20-17 FLATIRON WEST, INC 1770 LA COSTA MEADOWS DRIVE SAN MARCOS CA 92078 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 9,986,623.67 0.00 2. a. Extra Work 495,309.10 4,148.60 b. Adustment Comp. 36,760.91 0.00 3. Materials on Hand 4. Earned Subject to Retention 10,518,693.68 4,148.60 5. Mobilization 1,054,783.73 0.00 6. Total Work Completed 11,573,477.41 7. Deductions -2,000.00 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 11,571,477.41 4,148.60 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 4,148.60