Dept. of Trans. PROGRESS Serial No. Contract No. 21-355-15-53 11-288834 PROGRESS PAYMENT VOUCHER %complete: %time: 70% 58% Location: Federal Project: 11-SD-125-0.0/1.1 NONE Progress payment No. 013 Payment period ending: 12-20-21 FLATIRON WEST, INC. 16470 W. BERNARDO DR #120 SAN DIEGO CA 92127 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 10,178,622.67 820,052.75 2. a. Extra Work 153,869.03 4,447.56 b. Adustment Comp. 3. Materials on Hand 0.00 -194,033.00 4. Earned Subject to Retention 10,332,491.70 630,467.31 5. Mobilization 1,660,000.60 0.00 6. Total Work Completed 11,992,492.30 7. Deductions -84,707.88 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 11,907,784.42 630,467.31 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 630,467.31