Dept. of Trans. PROGRESS Serial No. Contract No. 22-021-15-09 11-288834 PROGRESS PAYMENT VOUCHER %complete: %time: 71% 62% Location: Federal Project: 11-SD-125-0.0/1.1 NONE Progress payment No. 014 Payment period ending: 01-20-22 FLATIRON WEST, INC. 16470 W. BERNARDO DR #120 SAN DIEGO CA 92127 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 10,472,707.67 294,085.00 2. a. Extra Work 176,793.26 22,924.23 b. Adustment Comp. 3. Materials on Hand 160,204.00 160,204.00 4. Earned Subject to Retention 10,809,704.93 477,213.23 5. Mobilization 1,660,000.60 0.00 6. Total Work Completed 12,309,501.53 7. Deductions -84,707.88 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 12,384,997.65 477,213.23 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 477,213.23