Dept. of Trans. PROGRESS Serial No. Contract No. 22-327-19-34 11-288834 PROGRESS PAYMENT VOUCHER %complete: %time: 95% 13% Location: Federal Project: 11-SD-125-0.0/1.1 NONE Progress payment No. 024 Payment period ending: 11-20-22 FLATIRON WEST, INC. 12121 SCRIPPS SUMMIT DRIVE #4 SAN DIEGO CA 92131 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 14,060,569.09 0.00 2. a. Extra Work 1,120,399.57 81,635.00 b. Adustment Comp. 79,062.92 0.00 3. Materials on Hand 7,569.00 0.00 4. Earned Subject to Retention 15,267,600.58 81,635.00 5. Mobilization 1,660,000.60 0.00 6. Total Work Completed 16,920,032.18 7. Deductions -84,707.88 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 16,842,893.30 81,635.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 81,635.00