Dept. of Trans. PROGRESS Serial No. Contract No. 19-291-13-25 11-2888U4 PROGRESS PAYMENT VOUCHER %complete: %time: 13% 11% Location: Federal Project: 11-SD-905-9.6/11.4 GCBI-000C(469) 11-SD-11 11-SD-125 Progress payment No. 003 Payment period ending: 10-20-19 SKANSKA USA CIVIL WEST CALIFORNIA DISTRICT INC 1995 AGUA MANSA RD RIVERSIDE CA 92509 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 7,993,440.45 5,916,930.45 2. a. Extra Work 66,979.50 1,171.50 b. Adustment Comp. 196,434.72 196,244.32 3. Materials on Hand 2,174,721.00 -171,129.00 4. Earned Subject to Retention 10,431,575.67 5,943,217.27 5. Mobilization 5,268,750.00 1,756,250.00 6. Total Work Completed 13,525,604.67 7. Deductions -20,520.00 -20,520.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 15,679,805.67 7,678,947.27 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 7,678,947.27