Dept. of Trans. PROGRESS Serial No. Contract No. 12-171-14-20 11-288904 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 97% 55% 11-SD-805-24.7/24.7 Federal Project: NONE Progress payment No. 10 Payment period ending: 06-20-12 DREAMBUILDER 1324 LAWSON LN PLACENTIA CA 92870 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 400,659.10 934.50 2.a. Extra Work 15,000.00 0.00 b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 415,659.10 934.50 5. Mobilization 23,587.00 0.00 6. Total Work Completed 439,246.10 7. Deductions -3,000.00 0.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 436,246.10 934.50 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 934.50