Dept. of Trans. PROGRESS Serial No. Contract No. 10-298-08-37 11-289304 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 32% 36% 11-SD-5-R39.8/R54.4 Federal Project: NONE Progress payment No. 04 Payment period ending: 10-20-10 SUKUT CONSTRUCTION INC 3156 VISTA WAY SUITE NO 205 OCEANSIDE CA 92056 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 560,503.67 198,674.75 2.a. Extra Work 4,998.67 4,998.67 b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 565,502.34 203,673.42 5. Mobilization 190,000.00 40,000.00 6. Total Work Completed 755,502.34 7. Deductions -3,000.00 -3,000.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 752,502.34 240,673.42 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 240,673.42