Dept. of Trans. PROGRESS Serial No. Contract No. 14-083-14-26 11-290304 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 18% 39% 11-SD-75-9.0/ .0 Federal Project: BRST-X073(99) Progress payment No. 05 Payment period ending: 03-20-14 PETERSON-CHASE GENERAL ENGINEERING CONSTRUCTION INC 1792 KAISER AVENUE IRVINE CA 92614 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 389,084.40 23,910.00 2.a. Extra Work 18,009.35 1,670.13 b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 407,093.75 25,580.13 5. Mobilization 127,500.00 0.00 6. Total Work Completed 534,593.75 7. Deductions 0.00 2,000.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 534,593.75 27,580.13 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 27,580.13