Dept. of Trans. AFTER ACCEPTANCE Serial No. Contract No. 15-078-07-20 11-290304 PROGRESS PAYMENT VOUCHER %complete: %time: 100% 100% Location: Federal Project: 11-SD-75-9.0 BRST-X073(99) Progress payment No. 015 Payment period ending: 02-12-15 PETERSON-CHASE GENERAL ENGINEERING CONSTRUCTION INC 1792 KAISER AVENUE IRVINE CA 92614 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 2,385,547.48 45,675.70 2. a. Extra Work 270,695.59 129,868.21 b. Adustment Comp. -68,329.84 4,709.32 3. Materials on Hand 4. Earned Subject to Retention 2,587,913.23 180,253.23 5. Mobilization 170,000.00 0.00 6. Total Work Completed 2,757,913.23 7. Deductions -378,298.03 34,751.97 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 2,379,615.20 215,005.20 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 215,005.20