Dept. of Trans. PROGRESS Serial No. Contract No. 14-055-15-05 11-290404 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 58% 28% 11-SD-94-14.9/30.0 Federal Project: ACNH-P094(59) Progress payment No. 05 Payment period ending: 02-20-14 GRANITE CONSTRUCTION COMPANY P O BOX 50085H STREET WATSONVILLE CA 950775085 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 5,922,330.60 556,414.80 2.a. Extra Work 112,753.24 25,944.89 b. Adjustment Comp. 53,564.88 -9,600.00 3. Materials on Hand 4. Earned Subject to Retention 6,088,648.72 572,759.69 5. Mobilization 1,200,000.00 60,000.00 6. Total Work Completed 7,288,648.72 7. Deductions -10,000.00 -5,000.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 7,278,648.72 627,759.69 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 627,759.69