Dept. of Trans. PROGRESS Serial No. Contract No. 09-112-14-16 11-290904 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 22% 16% 11-SD-5-R12.4/R16.1 Federal Project: NONE Progress payment No. 01 Payment period ending: 04-20-09 CAROLINO CONSTRUCTION CORPORATION 3035 EAST 8TH STREET NATIONAL CITY CA 91950 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 220,768.42 220,768.42 2.a. Extra Work b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 220,768.42 220,768.42 5. Mobilization 41,868.60 41,868.60 6. Total Work Completed 262,637.02 7. Deductions 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 262,637.02 262,637.02 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 262,637.02