Dept. of Trans. PROGRESS Serial No. Contract No. 18-053-07-37 11-292004 PROGRESS PAYMENT VOUCHER %complete: %time: 16% 13% Location: Federal Project: 11-SD-125-9.8/12.4 ACNH-P125(19) Progress payment No. 004 Payment period ending: 02-20-18 WESTERN RIM CONSTRUCTORS INC. 621 S ANDREASEN DR #B ESCONDIDO CA 92029 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 257,915.15 41,551.10 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 229,578.62 0.00 4. Earned Subject to Retention 487,493.77 41,551.10 5. Mobilization 210,000.00 0.00 6. Total Work Completed 467,915.15 7. Deductions -5,000.00 0.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 692,493.77 41,551.10 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 41,551.10