Dept. of Trans. PROGRESS Serial No. Contract No. 15-146-07-22 11-292304 PROGRESS PAYMENT VOUCHER %complete: %time: 12% 22% Location: Federal Project: 11-SD-805-0.9/1.1 STPI-805-1(628) Progress payment No. 002 Payment period ending: 05-20-15 CLEAN CUT LANDSCAPE 8406 N ARMSTRONG AVE CLOVIS CA 93619 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 102,227.74 99,221.74 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 102,227.74 99,221.74 5. Mobilization 78,726.50 78,726.50 6. Total Work Completed 180,954.24 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 180,954.24 177,948.24 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 177,948.24