Dept. of Trans. PROGRESS Serial No. Contract No. 17-331-09-25 11-292304 PROGRESS PAYMENT VOUCHER %complete: %time: PEP SAT Location: Federal Project: 11-SD-805-0.9/1.1 STPI-805-1(628) Progress payment No. 032 Payment period ending: 11-20-17 CLEAN CUT LANDSCAPE INCORPORATED 7726 N FIRST ST UNIT 137 FRESNO CA 93720 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 1,462,224.49 58,554.33 2. a. Extra Work 78,281.72 0.00 b. Adustment Comp. -6,977.00 -6,977.00 3. Materials on Hand 4. Earned Subject to Retention 1,533,529.21 51,577.33 5. Mobilization 157,453.00 0.00 6. Total Work Completed 1,690,982.21 7. Deductions -3,000.00 -3,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 1,687,982.21 48,577.33 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 48,577.33