Dept. of Trans. PROGRESS Serial No. Contract No. 18-233-16-15 11-292304 PROGRESS PAYMENT VOUCHER %complete: %time: PEP SAT Location: Federal Project: 11-SD-805-0.9/1.1 STPI-805-1(628) Progress payment No. 041 Payment period ending: 08-20-18 CLEAN CUT LANDSCAPE INCORPORATED 7726 N FIRST ST UNIT 137 FRESNO CA 93720 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 1,537,954.71 10,289.22 2. a. Extra Work 82,516.72 0.00 b. Adustment Comp. -6,977.00 0.00 3. Materials on Hand 4. Earned Subject to Retention 1,613,494.43 10,289.22 5. Mobilization 157,453.00 0.00 6. Total Work Completed 1,770,947.43 7. Deductions -12,000.00 -10,000.00 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 1,758,947.43 289.22 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 289.22