Dept. of Trans. SUPPLEMENTAL Serial No. Contract No. 18-277-13-40 11-292804 PROGRESS PAYMENT VOUCHER %complete: %time: 51% 65% Location: Federal Project: 11-SD-52-3.9/6.6 ACNH-P052(18) Progress payment No. 004 Payment period ending: 09-20-18 HAZARD CONSTRUCTION COMPANY 6465 MARINDUSTRY PLACE SAN DIEGO CA 92121 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 465,682.50 118,689.49 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 465,682.50 118,689.49 5. Mobilization 90,250.00 0.00 6. Total Work Completed 555,932.50 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions c. Reduction after 95% Comp. 9. Total pay to Contractor 555,932.50 118,689.49 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 118,689.49