Dept. of Trans. PROGRESS Serial No. Contract No. 18-354-18-18 11-292804 PROGRESS PAYMENT VOUCHER %complete: %time: 84% 100% Location: Federal Project: 11-SD-52-3.9/6.6 ACNH-P052(18) Progress payment No. 007 Payment period ending: 12-20-18 HAZARD CONSTRUCTION COMPANY 6465 MARINDUSTRY PLACE SAN DIEGO CA 92121 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 816,612.17 45,075.00 2. a. Extra Work b. Adustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 816,612.17 45,075.00 5. Mobilization 95,000.00 0.00 6. Total Work Completed 911,612.17 7. Deductions 8. a. Contract Retentions b. Unsatisfactory Retentions -5,220.50 -4,507.50 c. Reduction after 95% Comp. 9. Total pay to Contractor 906,391.67 40,567.50 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 40,567.50