Dept. of Trans. PROGRESS Serial No. Contract No. 12-171-14-56 11-293104 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 98% 55% 11-SD-78-15.5/R16.7 Federal Project: NONE Progress payment No. 12 Payment period ending: 06-20-12 GRANITE CONSTRUCTION COMPANY P O BOX 50085 WATSONVILLE CA 950775085 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 2,020,111.92 880.00 2.a. Extra Work 192,805.99 36,227.39 b. Adjustment Comp. -5,388.69 -5,636.62 3. Materials on Hand 4. Earned Subject to Retention 2,207,529.22 31,470.77 5. Mobilization 229,189.00 0.00 6. Total Work Completed 2,436,718.22 7. Deductions -33,857.70 0.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 2,402,860.52 31,470.77 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 31,470.77