Dept. of Trans. PROGRESS Serial No. Contract No. 08-269-13-22 11-293804 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 77% 91% 11-SD-15-20.5/28.0 Federal Project: NONE Progress payment No. 03 Payment period ending: 09-20-08 FCI CONSTRUCTORS JEFF TURNER 1770 LA COSTA MEADOWS DRIVE SAN MARCOS, CA 92078 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 2.a. Extra Work 766,038.58 251,314.73 b. Adjustment Comp. 3. Materials on Hand 0.00 -239,758.12 4. Earned Subject to Retention 766,038.58 11,556.61 5. Mobilization 6. Total Work Completed 766,038.58 7. Deductions 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 766,038.58 11,556.61 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 11,556.61