Dept. of Trans. AFTER ACCEPTANCE Serial No. Contract No. 10-026-07-31 11-295504 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 100% 100% 11-SD-163-0.7/2.5 Federal Project: NONE Progress payment No. 06 Payment period ending: 01-06-10 PATRIOT GENERAL ENGINEERING INC 5480 BALTIMORE DRIVE STE 204 LA MESA CA 91942 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 610,086.57 7,086.18 2.a. Extra Work 86,260.75 25,504.12 b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 696,347.32 32,590.30 5. Mobilization 6. Total Work Completed 696,347.32 7. Deductions -2,000.00 -1,000.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 694,347.32 31,590.30 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 31,590.30