Dept. of Trans. PROGRESS Serial No. Contract No. 10-326-15-00 11-295604 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 71% 84% 11-IMP-86-6.5/ .0 Federal Project: NONE Progress payment No. 03 Payment period ending: 11-20-10 HAZARD CONSTRUCTION P O BOX 229000 SAN DIEGO CA 921929000 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 270,359.80 96,144.00 2.a. Extra Work b. Adjustment Comp. 3. Materials on Hand 4. Earned Subject to Retention 270,359.80 96,144.00 5. Mobilization 40,000.00 2,000.00 6. Total Work Completed 310,359.80 7. Deductions -10,000.00 0.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 300,359.80 98,144.00 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 98,144.00