Dept. of Trans. SEMI-FINAL Serial No. Contract No. 11-117-17-00 11-295604 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 100% 100% 11-IMP-86-6.5/ .0 Federal Project: NONE Progress payment No. 06 Payment period ending: 12-23-10 HAZARD CONSTRUCTION P O BOX 229000 SAN DIEGO CA 921929000 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 389,563.85 0.00 2.a. Extra Work 5,052.14 3,862.50 b. Adjustment Comp. -2,940.05 -2,940.05 3. Materials on Hand 4. Earned Subject to Retention 391,675.94 922.45 5. Mobilization 40,000.00 0.00 6. Total Work Completed 431,675.94 7. Deductions -5,000.00 15,500.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 426,675.94 16,422.45 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 16,422.45