Dept. of Trans. SUPPLEMENTAL Serial No. Contract No. 09-348-08-31 11-296504 PROGRESS PAYMENT VOUCHER %complete: %time: Location: 99% 83% 11-SD-8-R0.7/2.9 Federal Project: NONE Progress payment No. 04 Payment period ending: 11-20-09 VULCAN MATERIALS COMPANY WESTERN DIVISION P O BOX 3098 SAN DIEGO CA 92163 Escrow No. 00000 Total Estimate This Estimate 1. Contract Itms Without Mobil. 2,078,339.91 67,545.19 2.a. Extra Work 209,205.46 207,773.17 b. Adjustment Comp. 64,364.27 -11,957.65 3. Materials on Hand 4. Earned Subject to Retention 2,351,909.64 263,360.71 5. Mobilization 200,000.00 0.00 6. Total Work Completed 2,551,909.64 7. Deductions -2,000.00 0.00 8. a.Contract Retentions b. Unsatisfactory Prog. c. Reduction after 95% Comp. 9. Total pay to Contractor 2,549,909.64 263,360.71 10. Reduction Amt to Escrow 11. Payment to Escrow 0.00 12. Net Pymt. this Estimate 263,360.71